Plumbing & Pipefitting RAMS & Method Statement
Plumbing and pipefitting RAMS need to cover hot works, pressure testing and legionella control alongside the routine trade risks. Principal Contractors on occupied or healthcare sites will look specifically at your water hygiene and commissioning arrangements.
M&E & Building Services
Plumbing & Pipefitting RAMS Pack
Risk assessment and method statement for plumbing & pipefitting.
- ✓ Full method statement, mobilisation to handover
- ✓ Traffic-light risk assessment, plumbing & pipefitting specific
- ✓ COSHH, PPE, permits, emergency procedures
- ✓ Editable Word document, your branding
Plumbing & Pipefitting Contractor Project Pack
The full pack Principal Contractors want to see.
- ✓ Everything in the RAMS Pack
- ✓ Registers, competency matrix, ITP, toolbox talks
- ✓ 19 appendices, incl. real inspection forms
- ✓ O&M, QA sign-off, submission checklist
Risk assessment
Hazards covered for plumbing & pipefitting
Every hazard below is assessed with likelihood, severity and residual risk after controls, presented in the traffic-light format Principal Contractors expect.
- ✓ Hot works - brazing, soldering and welding, with fire risk to adjacent materials
- ✓ Stored pressure during pressure and flushing tests
- ✓ Scalding from hot water systems and existing live services
- ✓ Legionella risk during commissioning, flushing and periods of stagnation
- ✓ Working at height for high-level pipework and plant connections
- ✓ Manual handling of pipe, valves, cylinders and plant items
- ✓ Confined spaces - plant rooms, ducts, risers and basements
Method statement
Sequence of work
The method statement follows the real on-site sequence, with controls tied to each step rather than listed separately at the end.
- Drawing review, isolation identification and permit arrangements agreed
- Isolation, drain down and confirmation of dead system
- Bracket and support setting out, pipework installation and jointing
- Hot works permit with fire watch where flame jointing is used
- Pressure test to specification with test records issued
- Chlorination, flushing and sampling to the water hygiene regime
- Commissioning, balancing and handover with O&M documentation
Competency
Cards and qualifications referenced
The competency matrix in the Contractor Project Pack is pre-populated with the qualifications a Principal Contractor will ask to see for this trade.
- ✓ NVQ Level 2 or 3 in plumbing or pipefitting
- ✓ Gas Safe registration where gas work is undertaken
- ✓ Hot works and fire watch training
- ✓ Confined space entry training where applicable